Proven Liaison & Compliance Record.

We have secured statutory plan sanctions, environmental approvals, and factory licenses for over 250 mega industrial facilities across South India.

Warehousing & Logistics

Mega Logistics Warehouse Setup (3,50,000 Sq.Ft)

📍 Sriperumbudur Industrial Hub, Tamil Nadu

Milestone Timeline
90 Days

⚠️ The Challenge

A global logistics group built a massive 3.5 Lakh sq.ft warehouse. However, construction commenced on layout variants before DTCP zoning sanctions were resolved, creating high exposure to municipal regulatory compounding fines.

📐 The Approach

Our in-house architects conducted an exhaustive pre-audit, correcting floor area indices (FSI) and drafting high-hazard sprinkler schematics to guarantee direct compliance with Fire Safety Act norms.

🏛 Liaison Strategy

Coordinated with local Town Planning offices to compromise deviations under standard zoning clauses, while fast-tracking Orange SPCB Consent-to-Operate parameters using express clearance routes.

Outcome Accomplished 100% Clearances Secured. Zero deviation queries or municipal fines.
Services Deployed DTCP Plan Sanction | Fire NOC | SPCB CTO
Automobile & Heavy Engineering

Metal Castings Plant Expansion (1,500 HP Power Line)

📍 SIPCOT Industrial Park, Hosur, TN

Milestone Timeline
75 Days

⚠️ The Challenge

A major Tier-1 automotive casting unit needed an urgent capacity expansion to install heavy furnace lines, requiring a massive electrical load expansion to 1500 HP under red-category SPCB guidelines.

📐 The Approach

Engineered chimney heights to meet TNPCB red-category threshold requirements. Configured detailed substation layouts and single-line electrical schematics matching state standards.

🏛 Liaison Strategy

Conducted concurrent presentations at the SPCB advisory board and Directorate of Industrial Safety & Health (DISH) inspectorate to demonstrate clean structural calculations.

Outcome Accomplished 1500 HP Grid energization completed. Factory licenses amended.
Services Deployed CEIG Substation NOC | DISH Amendment | SPCB CTO
Electronics & Medical Devices

Greenfield Medical Electronics Manufacturing Hub

📍 Sri City Multi-Product SEZ, Tada, AP

Milestone Timeline
120 Days

⚠️ The Challenge

A multinational medical device company required a pristine greenfield electronics cluster. Had a highly compressed 4-month commercial launch schedule tied to overseas manufacturing pipelines.

📐 The Approach

Utilized our pre-integrated single-window checklists to assemble clean layout schematics, zoning document certificates, and building plans with zero syntax errors.

🏛 Liaison Strategy

Directly coordinated with the Sri City SEZ Single-Window Clearance board and APPCB officials to fast-track Orange Category Consent to Establish approvals.

Outcome Accomplished CTE issued on Week 8. Factory launched exactly on schedule.
Services Deployed Single-Window Liaison | APPCB CTE | APIIC Plans